Dear Miss Banee,

I would like to draw your attention to this particular situation of
mine. I made an Airbox application on 19 June 2015. A colleague made an
Airbox application on 29 June 2015. I was initially told installation
would be done within 5 days on my premises. I was only informed of
circumstances causing a delay when I contacted you.

However, today my colleague received a team of Emtel technicians for the
Airbox installation while I am still in the waiting list. He lives at
Beau-Bassin. First-come-first-serve does not seem to apply here.

I re-phrase my statement into a question this time:

        Does Emtel have a different policy for villages?

How come someone who applied 10 days after me receives an installation
team at his doorstep while Emtel can't properly justify the installation
delay at Providence?

Regards,

-- 
​Ish Sookun
- Geek by birth, Linux by choice.
- I blog at HACKLOG.in.
https://twitter.com/IshSookun ^^ Do you tweet?
Received on Tue Jul 14 2015 - 13:26:23 PST

This archive was generated by hypermail 2.3.0 : Tue Jul 14 2015 - 13:27:01 PST